Updates to the new residence hall

The new residence hall is going up quickly and there are numerous updates to give. The building is now topped out and the efforts have been shifted to interior finishes. The walls are being stood up on 4th Floor and the basement floor slab is in the process of being poured. Window install began October 31. We should be seeing a partially weathertight roof by early November, and the cranes have left the site.

You may also like...